Route D over Center Creek

Hartman & Company, Inc.

Route D Bridge Demolition & Drilling

___________________________________________________________________________________________________________________________

Project Location: Webb City, MO     Jasper Co.

Demolition Dates: 04/08/2019-04/21/2019

Drilling Dates: 04/29/2019-06/13/2019

Bridge Work Completed: Completed over-water demolition of the existing Route D bridge. The project plans were created to limit the amount of debris that would fall into Center Creek and recycle all bridge materials that could be processed and sorted.

Drilling Work Completed: Operated a Volvo 250 with a

TR-40 LoDril attachment to drill 111 Linear Feet of 48" Drilled Shafts, 99 Linear Feet of 42" Rock Sockets, and 119 Linear Feet of Pre-Bore for Piling. Pictured is some of the large cores that were extracted during this job.

LINKS ABOUT ROUTE D BRIDGE DEMOLITION:

https://www.modot.org/jasper-county-route-dcenter-creek-bridge-replacement

 

https://www.joplinglobe.com/news/local_news/no-parties-interested-in-historic-center-creek-bridge/article_2b49cfa7-df2c-53d0-b354-a07bfb8e56ba.html

 

https://www.joplinglobe.com/news/local_news/construction-to-begin-shortly-on-route-d-bridge-over-center/article_69f22965-05ce-589a-b7e5-cc99aee9b79d.html

PHOTOS TAKEN BY JOSH KONRADE

© 2018 by Greg Bair Track Hoe, Inc.

  • GBTS Facebook
bottom of page